Over the past few weeks, our ARP team has been working on the following:

  • B26 elevated tanks have been dismantled and removed for disposal.
  • E1, E2, E3, and E4 Engines have been disassembled and removed from B26 (E1-E4 Powerhouse) for disposal.
  • B6 (Old Power Station) demolition is in progress with the B6 superstructure and OPS radiator fans removal approximately 80% complete.
  • Removal of decommissioned E5 & E6 Radiator fans located at B7 is approximately 15% complete.

Upcoming works for the next 4 weeks are expected to include:

  • Continued removal of B26 external equipment and exhaust piping.
  • Continued demolition of B6 (old Power Station) building.
  • B9 (injector workshop) relocation preparations are in progress. The existing injector workshop will be relocated to B26 to facilitate the demolition 0f B9.

    When demolition is occurring our neighbours and passersby may notice the following disturbances:

    • Demolition noise from the construction equipment, which will be mitigated by limiting work to daytime production hours only (ie. 7:00am to 4:00pm)
    • Localised airbourne dust, which will be mitigated by mist mechanisms and stockpile covers
    • Increased truck traffic along Cemetery Road to remove building materials and engine components, which will be mitigated by flag men while trucks enter and exit the demolition site.

    SAFETY & SIGNAGE
    Project safety signage and project barriers are in place surrounding all demolition and work/project areas. All project areas are limited to the BELCO Serpentine Road campus only.

    We ask our neighbours, passersby and campus visitors/guests to observe all safety signage and to not enter or attempt to enter any marked project areas in order to protect the safety of everyone.