ARP Update 14

Nov 4, 2022

Over the past few weeks, our ARP team has been working on the following:

  • B26 exterior dismantling is complete
  • B26 exterior louvers are demolished
  • B26 pedestal demolition test successful

Upcoming works for the next 4 weeks are expected to include:

  • Continued demolition of B6 (Old Power Station) building
  • Removal of B26 E1 – E4 engine pedestals 
  • Demolition of Centane Tanks 

    When demolition is occurring our neighbours and passersby may notice the following disturbances:

    • Demolition noise from the construction equipment, which will be mitigated by limiting work to daytime production hours only (ie. 7:00am to 4:00pm)
    • Localised airbourne dust, which will be mitigated by mist mechanisms and stockpile covers
    • Increased truck traffic along Cemetery Road to remove building materials and engine components, which will be mitigated by flag men while trucks enter and exit the demolition site.

    SAFETY & SIGNAGE
    Project safety signage and project barriers are in place surrounding all demolition and work/project areas. All project areas are limited to the BELCO Serpentine Road campus only.

    We ask our neighbours, passersby and campus visitors/guests to observe all safety signage and to not enter or attempt to enter any marked project areas in order to protect the safety of everyone.